MTN Bus Facilty Update

From the developer NEOO regarding the bus facility…. MTN has decided to cancel the PA (purchase agreement) with Hennepin County – however that request hasn’t been accepted. The cost estimates which came back last week for soil remediation, stormwater management, and soil corrections increased the overall construction budget by $3.0M! This significant cost increase prevents MTN from moving further with the project despite their willingness to accommodate changes requested by the community. We thank you being an ally for us in respect to reaching out to neighbors and concerned residents. Although we only had two occasions for conversation, we heard a lot of feedback which helped us change project design and operational plans. 